If a worker completes a task in 8 days, how many days will 5 workers take to complete the same task?

A. 1.6 days
B. 2 days
C. 1.5 days
D. 2.5 days

Explanation:

Work time is inversely proportional to the number of workers: 8/5 = 1.6 days.