If 12 men can complete a work in 8 days, how many days will 16 men take to complete the same work?

A. 5 days
B. 6 days
C. 7 days
D. 4 days

Explanation:

Explanation: Work is inversely proportional to the number of workers. 12×8 = 16×days, so days = 6. Other options are incorrect.